Edwards Place Phase 2
Type of Project:
Residential
Scope of Work:
SWPPP Controls, Clearing & Grubbing, Grading, Water Main Offsets, Hydrant Assembly + Water Services, Sewer Services, Storm Drain, R-Tank Underground Detention System, Concrete Ribbon Curb, Concrete Pervious Pavers, SCDOT Asphalt ROW, Signage + Striping
Location:
675 McCants Drive
Mount Pleasant, SC 29464
Owner:
Edwards Place, LLC
General Contractor:
JWC worked directly for the developer
Engineer:
Cline Engineering
Project Overview:
Nestled in the heart of Mt. Pleasant’s historic Old Village, Edwards Place combines timeless charm with thoughtful, modern development. This 2.0-acre community features five custom homesites, a shared HOA space, and a beautifully crafted shared concrete pervious paver driveway — all designed with an eye toward both beauty and functionality.
JWC expertly navigated the site’s unique challenges, including tight space constraints and critical stormwater management needs. By installing an engineered underground R-Tank SD Stormwater Detention System, we preserved valuable land while providing sustainable water management solutions.
Utility installation required two open cuts across McCants Drive, handled with minimal disruption to traffic. Despite encountering an unexpected watermain conflict, our crews quickly adapted, installing vertical offsets and completing the work in just three days.
The finishing touch — a concrete ribbon curb and pervious paver driveway, delivering curb appeal while supporting site drainage.
Through strategic planning, seamless coordination, and efficient execution, the Edwards Place Phase 2 site was delivered ready for homebuilding — preserving the spirit of the Old Village while preparing for its future.




Challenges & Details:
- To install the new fire hydrant, night work required.
- Two (2) new 8″ water main offsets required due to utility conflict of the two (2) new 6″ sewer services.
- Small site, therefore storage of stormwater acquired through the engineering and construction of an underground detention system located under the shared pervious paver driveway.